PRG Logo Portishead Railway Group

 Re-Opening the Portishead Line – Frequently Asked Questions


MetroWest, created in 2013 by the four Councils that used to be Avon (CUBA), links together all Bristol’s rail services, to deliver two reopened passenger lines, Portishead and Henbury, half hourly train services across the West of England and up to ten new stations. Reopening the Portishead line is the key project in MetroWest Phase 1.


The four West of England councils have spent about £32 million on the project so far (June 2024) and the £152 million budget has been secured from devolved local growth funds, the Department for Transport and the four councils’ own money.


In 2002, Quays Avenue cut off the final 400 metres of the line. The station, bus interchange and drop off car park will be where the Quays Avenue/Phoenix Way roundabout currently is, with Quays Avenue diverted westwards around it to a new roundabout. There will be a 400 metre walkway with parking along the old track bed from the station site to Waitrose.


Pill station will be rebuilt on the existing site, with improved access, a car park and a small drop off area.


GRIP is the Guide to Railway Investment Projects - Network Rail’s project management system. All railway infrastructure projects have to follow this eight stage process. The Portishead line reached GRIP 3 in 2010 as a single line. Today, as part of the whole MetroWest project, GRIP 5 is just about complete. The complexity and breadth of this work is illustrated by the Portishead line’s inclusion in the London Crossrail timetabling!


A Development Consent Order is the means of obtaining the planning powers to build and operate developments categorised as Nationally Significant Infrastructure Projects. It replaces other consents such as planning permission and compulsory purchase orders.


Reopening the Portishead line is considered a Nationally Significant Infrastructure Project because part of the track fell out of Network Rail use. The DCO is a lengthy statutory process, with numerous public consultations, taking several years to complete. It is a massive undertaking to prepare – 27,000 pages.


Good question! Re-opening any railway line is not simple. There is a mountain of political, financial, legal, geographical, planning, transport strategy, engineering, environmental, technical and risk issues that have to be dealt with. All have to move forward in unison to deliver a working railway.


Engineering for MetroWest has had to interlink with other major rail projects such as electrification, the four tracking of Filton Bank, Bristol East junction signalling and the new Intercity trains.


The formation of MetroWest in 2013 enabled North Somerset Council and WECA (Bristol, BANES and S.Gloucestershire) to all move forward together with real momentum, with legal agreements in place to ensure this continues. NSC are the project sponsor for the key Phase 1B Portishead line project, WECA for the Phase 1A Severn Beach & Bath enhancements.


The DCO took considerably longer to prepare than expected, due mainly to the complexity of the numerous environmental impact assessments. The completed DCO is 27,000 pages in length and contains more than 17,000 pages on the environmental aspects! [The Times August 2024]


The DCO was submitted to the Planning Inspectorate in December 2019. The Dept. for Transport then delayed the outcome by a further 18 months before approving the DCO on 14 November 2022.


After the lengthy DCO delays, the total budget was confirmed in 2023 as £152 million. An indication of how the costs add up was provided in the 2017 GRIP 3 report.


The project was fully funded until the 2024 delays and funding cuts. About £32 million has been spent to get this far:


Local Growth Fund 2013                         £18.9 million

Economic Development Fund 2013 &19   £49.5 million

WECA & 4 local Councils                          £36.1 million

Dept. for Transport CP6 RNEP 2019         £31.9 million

DfT Additional contribution 2023              £15.6 million














In July 2024, the Government axed the Restoring your Railways fund, resulting in the loss of the Dept. for Transport’s £15.6 million sum. A review of funding is underway and should complete by October 2024.


Trains should have been running by mid-2026, but the funding review announced in August 2024 will delay this.


The trains will be similar to those used on the Severn Beach line – Class 166 units. There will be three carriage trains initially, with a top speed of 90 mph and a capacity of 270 seats plus 90 standing.


The preferred option was to operate trains every half an hour at peak times and hourly off-peak, from Portishead to Bristol Temple Meads calling at Pill with a 17 minute journey time. This was revised in April 2018 to roughly an hourly service, 18-20 trains per day with a 23 minute journey time.


About 380 parking spaces will be provided at Portishead (90 more than the Nailsea & Backwell station car park). Work on pricing and managing parking on local roads is part of the DCO/GRIP process work.


There are three locations where unofficial paths cross the track. These are not Rights of Way, are labelled as temporary paths and will close when the line reopens.

The cycle access was allowed using temporary way-leaves, which can be revoked by Network Rail when they wish to operate the railway. The M5 tunnel is wide enough to contain a single track and the cycle track. The docks car park crossing is a temporary crossing, with a planning condition for the docks to construct an over bridge when the line is rebuilt.


The track is regularly cleared to a 10 metre width to access the infrastructure along the line.


GRIP 5 and the Full Business Case are more or less complete, but the General Election and spending review by the new government have delayed the approval of the Full Business Case.


The old rails are being removed (August 2024) having been acquired by Avon Valley Railway.


The Government is reviewing the funding for the reopening. To influence that decision, PRG is raising a Public Petition that has to be presented in Parliament by our MP, Sadik Al-Hassan. The Bristol Rail Campaign is also organising a rally at Temple Meads (August 2024).


Three business cases are required before construction can start, two of which have been completed:


Approved 12th September 2014 after 12 months’ work and confirms:


Cost changes and the complexity of the environmental assessment and Avon Gorge works delayed completion until late 2018.


Currently under review, due to delays and funding changes, but is required before construction can start, comprising:



Bristol 30% BANES 15% South Gloucs 5% North Somerset 50%


As we know, these risks have already delayed things at times! However, they haven’t stopped the

project and actually create a strong financial spur for the four councils to ensure the project is delivered.



Where can I find more Information?

One of the most useful documents about the Portishead & Pill line can be downloaded here. It’s 7 years old, and parts are out of date, but it offers good information about the features of the reopening scheme.

https://metrowestphase1.org/wp-content/uploads/2017/09/27543-metrowest-phase-1-campaign-final-web-version.pdf


Peter Maliphant

Membership Secretary

15 August 2024

 Updated August 2024

Top